ACICS is committed to collaborating with the institution in effecting a smooth and deliberate path toward meeting ACICS criteria and maintaining an accreditation status. The new grant process may take from nine months (if there are absolutely no areas of non-compliance) to 24 months. Shown below is a summary of the typical process.
RESPONSIBLE
PARTY
|
ACTION STEP
|
Institution
|
STEP 1 - Required documents.
The following documents are available for download prior to the purchasing of
this application Each institution is provided a deadline for when the first set of
documents are required. Institutions that submit documentation after their
scheduled deadline may be assessed a late fee.
DOCUMENTS DUE BY SCHEDULED DEADLINE
• Explanation
• Future Plans
• Campus Effectiveness Plan (CEP)
• Academic Credit Analysis
• Self Study Narrative
DOCUMENTS DUE TWO WEEKS PRIOR TO SCHEDULED VISIT DATE (See STEP 6)
• Faculty and Staff Summary
• Inventory of Equipment
• Catalog
• Program Update Form
|
Institution
|
STEP 2 - Purchase the New Grant (Reevaluation Application) products.
Logon using your institution's username and password.
(DO NOT re-register. If you are unsure of the institution's login information, please contact ACICS)
See Instructions for Purchasing an Application.
• New Grant (Reevaluation, per main and branch)
• New Grant Learning Site Surcharge *
• New Grant Specialized Programs Surcharge **
*Institutions with learning sites must also purchase a New Grant Learning Site Surcharge. When purchasing, adjust the quantity to accurately reflect the number of Learning Sites aligned with the institution.
**Institutions must also select New Grant Specialized Program Surcharge item and adjust the quantity to reflect the number of non-business programs approved for the institution.
|
Institution
|
STEP 3 - Upload and submit the following documents (See Step 1)
Instructions for Uploading Documents.
• Explanation
• Future Plans
• Campus Effectiveness Plan (CEP)
• Academic Credit Analysis
• Self Study Narrative
|
ACICS
|
STEP 4 - Review submitted documents. ACICS staff will review documents submitted by the institution and refer
to the Academic Credit Analysis when conducting a program audit.
|
Institution
|
STEP 5 - Schedule a visit.
ACICS staff will work with the institution to schedule the visit date and conduct
a program audit of all active programs with expected enrollment at the time
of the visit.
|
Institution
|
STEP 6 - Submit updated information.
Two weeks prior to the scheduled visit date, institutions are required to submit update information which consists of:
• Faculty and Staff Summary
• Inventory of Equipment
• Catalog
• Program Update Form
• Class Schedule that will be in effect on the day(s) of the
visit. Include time, instructor, class name (not
abbreviation), room number, and enrollment
See Instructions for Purchasing an Application
|
Institution
|
STEP 7 - Send updated information to each team member.
Institutions are responsible for sending New Grant (Reevaluation)documents
(See Step 3 and Step 6) via a compact. disc (CD) or flash drive at least two weeks prior to the visit.
|
Institution
|
STEP 8 - Onsite evaluation visit.
When an institution has submitted a satisfactory self-study and other required documentation, the office of the Executive Director will appoint a team to visit and evaluate the institution. The institution is notified of the composition of the visiting team. For additional information on the evaluation site visit, click here.
|